Image

The rescuers plan to create an escape passage by inserting a large-diameter mild steel pipes through the rubble and create an escape passage for the trapped workers.

Rescue operations are underway on the third day to evacuate 40 workers trapped inside a collapsed tunnel in Uttarakhand. Excavators have been removing debris for two days and cutting down the rocks to make a way to reach the workers, who have been trapped in the tunnel since Sunday morning.

Disaster Management Secretary Ranjit Kumar Sinha said authorities have set a target of rescuing the trapped labourers by Tuesday night or Wednesday.

The workers, from states including Jharkhand, UP, Orissa, Bihar and other states are being provided with food, medicines, and other essential supplies. Trucks carrying pipes have arrived to create a platform for drilling and inserting metal pipes to reach the trapped workers.

The region is prone to landslides, earthquakes and floods and the incident follows events of land subsidence in the state that geologists, residents and officials have blamed on rapid construction in the mountains.

Auger tunnel boring machines are used to install piping underneath roadways, tunnels and other infrastructure. Auger boring can be used to install pipes and casings in mining lengths up to about 500 feet and diameters up to about 60 inches.

Scientists and academicians have said that the Silkyara tunnel is being built in an area comprising limerock, a sedimentary rock, making it prone to recurrent collapses.

It uses a revolving cutting head that is located at the leading end of an auger string. The auger is laid into a launch pit on tracks and is slowly pushed through the ground by the machine.

The collapse of the Silkyara tunnel has reignited concerns among environmentalists and the scientific community about the devastating impact of extensive construction in an area, which is prone to landslides.

As per reports, the rescuers have already initiated the process of inserting large-diameter steel pipes of a diameter of 900 mm through the rubble using an auger machine to rescue the workers.

The incident unfolded after an under-construction tunnel built between Silkyara and Dandalgaon on the Brahmakhal-Yamunotri National Highway in the Uttarkashi district collapsed trapping 40 workers inside.

Image

In the landslide-zone map presented by ISRO, Rudraprayag district has been shown to be very vulnerable to disasters but the government has not taken any steps towards reducing them, former advisor to the State Planning Commission, Harshapati Uniyal, said.

The collapsed area is spread over 30 metres and located 270 metres inside the tunnel from the Sikyara side. The tunnel, supposed to be 4,531 metres long when ready, is already built 2,340 metres from Silkyara side and 1,750 metres from Barkot side.

According to Geologist SP, tunnelling in such areas is only effective when all protocols are strictly adhered to. However, in the case of Uttarkashi, there are only two potential reasons for this collapse: blind shear zone, thin zone within the Earth’s crust or upper mantle that has been strongly deformed, and the use of explosives for tunnelling.

Miller's Tooling Pty Ltd proudly offers "TaeguTec" premium quality lathe carbide inserts, turning toolholders and boring bars in our off-the-shelf product selection. Miller's Tooling Pty Ltd has been appointed TaeguTec's exclusive distributor for the SE QLD region. Please select from the various types in the drop down boxes above. PLEASE NOTE: INSERTS COME IN PACKS OF 10 ONLY SUITS TOOLHOLDERS: TaeguTec SDJCR 0808 E07 TaeguTec SDJCR 1212 F07 TaeguTec SDJCR 1616 H07 TaeguTec SDJCR 2020 K07 TaeguTec SDJCL 0808 E07 TaeguTec SDJCL 1212 F07 TaeguTec SDJCL 1616 H07 TaeguTec SDJCL 2020 K07 TaeguTec SDNCN 0808 F07 TaeguTec SDNCN 1010 F07 SUITS BORING BARS: TaeguTec S10K SDUCR 07 TaeguTec S12M SDUCR 07 TaeguTec S16R SDUCR 07 TaeguTec S10K SDUCL 07 TaeguTec S12M SDUCL 07 TaeguTec S16R SDUCL 07 Please contact Miller's Tooling Pty Ltd for further technical advice and service. Ph: 07 3806 0996 Fax: 07 3806 0997 Email: [email protected]

Officers from a rescue team are seen during a rescue operation after a portion of a tunnel collapsed in Uttarakhand. (Credits: Reuters)

The trapped workers are being sent dry food items and essential commodities through pipes. Medical experts say that the labourers, who have been stuck for more than 48 hours, are confronting both physical and physiological challenges.

There were around 50 or 60 workers inside the tunnel and around 10 or 20 of them got out after their shift ended as they were closer to the exit and the rest were trapped after the collapse.

The pipes will be pushed in using the horizontal drilling equipment called an auger machine to create an escape passage for the workers. Officials said around 21 metres of slab blocking the tunnel has been removed and a 19 metres passage is yet to be cleared. A platform is being prepared for an auger machine to drill horizontally and push the pipes through the debris and evacuate the workers.

Image

Uttarakhand Chief Minister Pushkar Singh Dhami visited the tunnel site on Monday to check the rescue operations being carried out and inspected the site along with officials. He said he is closely monitoring the situation and informed that food, water and oxygen are being supplied to the people trapped inside.